Converting a licensure from skilled nursing to another form of care is not for the faint of heart. With vision, planning and effective communication, however, a team of professionals can expedite a smooth transition. In this article, we’ll share the top 10 tips when converting licensure status.

1. Assessing existing conditions

senior living community dining room
Depending on the type of licensure being pursued, requisite standards may have to be met for corridor width, door hardware, resident room size, common space per resident and more. (Photo courtesy of Hoffman Planning, Design & Construction Inc.)

The first step in transitioning a skilled nursing facility to another licensure type is assessing the existing conditions of the building. It’s crucial to determine whether the current structure can support the new use.

One particular concern is related to fire protection elements. For instance, although a community-based residential facility, or CBRF, requires smoke detectors connected to a fire alarm panel in each resident-occupied space, SNFs might not have this requirement. Additionally, considerations such as corridor width, window operation, door hardware, resident room size, a resident’s ability to evacuate without assistance, and common space per resident must meet the requisite standards.

2. Owner responsibilities

Owners have significant responsibilities in this transition. Understanding licensing requirements and the timeline for submissions to the authority having jurisdiction, or AHJ, is paramount.

Engaging in in-depth operational discussions with the architect is essential to incorporate necessary elements into the design. Owners should lead the discussions regarding their expectations for systems such as wander management or nurse call; heating, ventilation and air conditioning; and emergency power backup. Additionally, they need to ensure that changes in procedures, such as fire safety plans, are in place for staff members during construction, to ensure a smooth and compliant transition.

3. Life safety during construction

Maintaining life safety during construction in an occupied building is necessary for both residents and staff members. Establishing secure construction zones is vital to prevent residents from entering hazardous areas.

Maintaining egress paths is key, as is retaining fire protection systems. Those measures are important because they allow you to ensure that occupants remain safe throughout the construction process.

4. Challenges with occupied buildings

older woman looking at a senior living community construction site.
To make licensure transitions more bearable to residents, consider creating a viewing gallery where residents can watch progress on the work being done. (Photo courtesy of Hoffman Planning, Design & Construction Inc.)

One of the major challenges during transition is minimizing disruption to residents. To mitigate this challenge, create viewing areas where residents interested in the construction can observe the progress. Offering guided progress tours when it is safe to do so also can help.

Ensuring that support spaces, such as those for dining, bathing and therapy, remain operational is necessary. Developing clear phasing plans showing all required life safety items in place once construction starts also is imperative.

The sad reality is that some facilities have seen an increase in deaths during extensive remodels due to the stress and anxiety caused by the disruption. It might be necessary to temporarily relocate those residents who would have trouble adapting, to minimize the effects of construction activities on their mental, physical and emotional health.

5. Importance of working with the authority having jurisdiction

Engaging with the AHJ early in the process is fundamental for a smooth transition, as is reviewing and confirming that interpretations of requirements are in alignment. Identifying and seeking approval for necessary variances early can prevent project delays.

This is especially true in buildings that will have multiple occupancy types, with licenses resulting in required building separations.

6. Approvals and inspections

Obtaining consensus with code officials on the overall plan and any necessary variances is vital for the transition. Ensuring equivalent building construction ratings through documented components when existing materials lack UL (Underwriters Laboratories) listings can be challenging but necessary.

Addressing potential pitfalls, such as exceeding the building’s allowable areas, requires finding equivalent life safety measures. For example, if the existing building slightly exceeds allowable building areas, then enhancing fire / smoke separations and increasing the number of exits might provide an equivalent safety tradeoff.

7. Building code compliance

Compliance with building codes is a critical aspect of transitioning from a SNF to a CBRF. Many states have adopted the International Building Code suite of codes but also may have specific state building codes that must be adhered to.

Confirming the architect references the correct codes and reviews assumptions with the AHJ is essential. Inspections should occur at pivotal construction milestones, and all sign-offs must be completed before occupancy.

Buildings currently licensed as SNFs often are easier to downgrade to a less intensive license because SNF occupancy life safety requirements often are the most stringent in the code. That is not always the case, however (see No. 1, smoke detection)!

8. Handling hazardous materials

It’s important for your team to document existing materials in place and to conduct an assessment to identify hazardous materials, such as asbestos.

Before modifying the building, all hazardous materials must be abated or encapsulated, adding time to the overall schedule. This process requires detailed coordination between the owner, construction manager and contractor to ensure safety and compliance with regulations, ultimately establishing a construction schedule that accounts for those critical steps.

9. Systems coordination

Also, be sure you understand how all mechanical, electrical and plumbing systems are integrated throughout the building. Guaranteeing that all vital systems, such as for water, fire protection, mechanical, nurse call and wander management, remain operational in occupied areas requires careful planning and coordination to maintain functionality and safety for residents while construction is ongoing.

This approach helps ensure a seamless transition without disrupting essential services.

10. Effective communication

When switching a facility’s licensure, constant communication among project team members is critical, from licensing requirements to necessary building revisions and more. (Photo courtesy of Hoffman Planning, Design & Construction Inc.)

Effective communication is paramount throughout all phases, from discovery to construction completion. Clearly understanding and communicating licensing requirements, necessary building revisions, the effect on the occupants and cost changes ensures that everyone is on the same page. Defining and documenting responsibilities, especially if the owner manages certain aspects of the work (such as moving out furniture or residents, removing materials or installing finishes), is essential to avoid confusion and overlap. Being certain that construction bids are accurate and avoid scope overlap will serve you well.

Owners and architects must work together with the AHJ to clearly demonstrate the project’s intent and compliance, increasing the chances of a smooth and successful transition.

Path to success

Understanding the complexities of converting existing buildings, especially those constructed before current codes, is crucial. Thoroughly investigating existing conditions and adhering to requirements for the new license status is essential. When an organization applies for a new license, even if it already has a license for another level of care, the application often undergoes higher scrutiny. Depending on the age and type of construction used initially, the new requirements may be more than anticipated.

Effective communication between the owner, architect, construction manager and code and building officials is key to avoiding misunderstandings and identifying unique requirements, ensuring a successful project.

Changing licensure in an existing building is complex and necessitates careful coordination, communication and planning. Use this as a guide to success!

Julie Heiberger is a senior project architect and the senior living market leader for Hoffman Planning, Design & Construction Inc. With more than 25 years of experience, her expertise centers on designing sustainable senior living communities that address the latest care models and industry trends. A member of the American Institute of Architects and the National Council of Architectural Review Boards, Heiberger received her Master of Architecture degree from the University of Wisconsin–Milwaukee. Email Julie at [email protected].